Not The Cheapest Bid: Prosper Lines Up A $287,625 Fix For The Raymond Park Dam

Prosper Roads & Infrastructure

Not The Cheapest Bid: Prosper Lines Up A $287,625 Fix For The Raymond Park Dam

Prosper Town Council votes Nov. 24 on a $287,625 Raymond Park dam repair contract. Garret Shields was third on price but won on a 40-day timeline.

Interactive mode

See this story, step by step.

The same reporting, built as you scroll. Go at your own pace.

Prosper's Town Council is scheduled to vote Tuesday, Nov. 24, on a $287,625 contract to repair the earthen dam along the northeastern edge of Raymond Park, about 150 yards west of Coit Road. Town staff recommend hiring Garret Shields Infrastructure, a Garland company, even though two other contractors offered to do the job for less.

The repairs would replace the dam's drainage pipes and add a concrete junction box, a structure where drainage lines meet. Crews would also install a chimney drain, which collects water seeping through the inside of an earthen dam so it doesn't weaken the dirt. Then they would pack in compacted clay and line the slope with riprap, a layer of large rocks that keeps water from eating away at the bank.

Why the higher bid came out on top

Five companies responded when the town took proposals in October. The lowest price came from Bernal Commercial Construction of Grand Prairie at $249,970, followed by Precision Road Services of Southlake at $256,480. Garret Shields came in third on price at $287,625, and a fifth proposal of $477,800 from Southern Development Corporation was ruled non-responsive.

Don’t miss what’s changing in Prosper.

Get updates on new businesses, city decisions, development projects, and local spending. One clear email every Wednesday.

Free newsletter. Unsubscribe anytime.

Prosper Greenlights Saddle Creek Shops While Fishtrap Car Wash Gets Rejected ↗

The town did not choose on price alone. Its scoring gave 65% of the weight to cost, 25% to how fast the work would get done and 10% to qualifications. Garret Shields promised to finish in 40 days, while the cheaper proposals estimated 130 and 150 days. That timeline, plus the top qualifications score, gave Garret Shields the highest total, 9.08 out of 10, against 8.00 for Bernal. The staff report calls Garret Shields "the lowest responsible bidder."

Under the contract, work would start within 10 days of the town's go-ahead and wrap up most of the job within 30 days, with another 10 days to finish punch-list items. The contractor would also owe a two-year warranty on the work.

Over the original budget

Staff say the price is within the engineer's estimate but pushes the total project cost above the original $350,000 budget. The town's October financial report shows about $101,000 of that budget already spent or committed. According to the staff report, the dam repair account covers 78% of this contract, and the rest would come from savings on the Doe Branch Trails project.

The contract is on the council's consent agenda, the list of routine items approved together in one vote unless a council member pulls one out for discussion. Parks and Recreation Director David Angeles signed the staff report, and the council meets at 6:15 p.m. at Town Hall.