"Three Years Later, Still Nothing": Princeton's $65 Million Rec Center Waits For 2028 As Parks Board OKs $17,000 Staff Fitness Room
Princeton's $65 million rec and aquatic center waits on the second $54 million parks bond sale, now projected for 2028. Parks Board members pushed back Nov. 3 as a $17,000 fitness room was approved.
Interactive mode
See this story, step by step.
The same reporting, built as you scroll. Go at your own pace.
Princeton's planned recreation and aquatic center is waiting on the second half of the city's $108 million parks bond, which city staff now project selling in 2028, and members of the Parks and Recreation Advisory Board told staff on Nov. 3 that residents are tired of waiting.
"So we are now three years later, still nothing and now nothing till 2028," one board member said. "So it's just very disappointing."
Later that night, the board approved about $17,000 in fitness equipment for a workout room in the city's new parks and recreation building. The purchase set off a long debate over whether city employees should get another fitness room while residents still have no rec center.
Where the bond money stands
Voters approved the parks bond in November 2023. Parks and Recreation Director Chase Bryant walked the board through a new internal dashboard tracking the program. The city sold $54 million in bonds in 2025, and the second $54 million sale is projected for 2028.
Of the $108 million, $65 million is set aside for the recreation and aquatic center, about $5.3 million for the parks and recreation maintenance building and $37.7 million for outdoor sports and park projects.
Bryant said construction documents for the rec center are 95% complete. Site and civil work, including the flat work and infrastructure, is expected to start next year, with the building itself to follow once the second bond sale comes through.
Other bond projects are further along. Bryant said Phase 2 of J.M. Caldwell Sr. Community Park, with soccer and multipurpose fields, is about 95% complete and tracking toward a Nov. 12 completion date. JJ Booker Park is about 74% to 75% complete, with construction set to wrap up Dec. 31. The new parks and recreation building is expected to be finished by the end of November, with staff moving in between Thanksgiving and Christmas.
Why the rec center slipped
Bryant said the rec center was always planned for the second round of bond money, originally scheduled for 2027, because a project that size takes close to two years to design. Construction alone is roughly $60 million, he said, and the city cannot commit that money before the bonds are sold.
He gave several reasons the second sale moved to 2028. When the bond was approved, the city's tax rate was cut by 10 cents, which he said pushed the bond sale out further. Council also made the other parks the priority. "Council sets our priorities and what the priorities have always been were the parks first," Bryant said. A police training facility planned for the same site added time, and Bryant pointed to turnover in city leadership. New city management arrived in February 2024, he said, and the first bonds were not sold until 2025.
The project itself has changed size. Bryant said the original site next to the fire station was designed for a 30,000 to 35,000-square-foot rec center, while current plans call for a 64,000-square-foot rec center with a 24,000-square-foot aquatics area. He also said the city had to go back last October for a half-million-dollar change order with its architect, Gensler, after the project was scaled back from what was going to be a $100 million facility to $60 million. He said the City Council has the final say on those decisions. The advisory board makes recommendations but does not set the city's priorities.
Board member Anthony Lynch said a sign next to the fire station advertised a future aquatic center and that the project "was presented as shovel ready." To "maintain trust," he said, the city needs to be "very open about where things truly are" when it asks voters for bonds in the future.
Board member Maxine Ellis recalled former City Manager Michael Mashburn showing plans for the center and saying it was "coming soon, groundbreaking soon. And again, where are we now?"
Bryant said the original plan would have sent all $108 million to the rec center, leaving no other parks under construction, and that council's direction was to get the smaller parks to residents first.
The $17,000 fitness room
The fitness equipment comes from Marathon Fitness and includes a treadmill, a rower, free weights, a multipurpose rack, a medicine ball and a few smaller pieces. Bryant said the city gathered three quotes. Marathon's $17,000 price includes installation, while one quote ran upward of $50,000 and another did not include installation. The purchase uses furniture, fixtures and equipment money already approved for the building, and Bryant said any of that money left over would go back into the bond for other projects.
Bryant said the fitness room was part of the design-build plan the council approved and that other city employees can use it, not just parks staff. The police facility also has a fitness room.
Some board members said the timing looks bad to residents. "That's $17,000 worth of equipment. I think that that's a stretch when citizens do not have a rec center," one member said. Another said residents see it as "bad timing" after "broken promises."
Others defended it. "17,000 on workout equipment is not a lot," one member said, and another said it could help the city keep employees: "If you retain one headcount, you've paid for that." One member noted that the board had already approved the building's design, including the fitness room, months earlier.
The board approved the purchase. It will not meet in December, and its next meeting is Jan. 6, 2027, the first under its new schedule of meeting on the first Wednesday of each month.