$55 Million In The Bank And Nobody Steering: Princeton Creates A Job To Drive Its Bond Projects

Princeton City Hall & Decisions

$55 Million In The Bank And Nobody Steering: Princeton Creates A Job To Drive Its Bond Projects

Princeton City Council votes 6-0 to add a bond-funded Capital Improvement Program Manager to deliver library, park and other bond projects instead of leaning on department heads and consultants.

Princeton City Council voted 6-0 on Monday, Nov. 23, to create a Capital Improvement Program Manager, a full-time city job whose only focus is getting bond-funded projects designed, built and finished. Alternate City Manager David Hall, who brought the proposal, told council that no one on staff currently owns that work, even with tens of millions of dollars in bond money waiting to be spent.

Right now, Hall said, some of the city's largest projects are being led by department heads with other full-time jobs, including the parks director and the director of public safety. He called that arrangement "fairly unusual" and said those leaders should be the people a project is built for, not the people running it. "They are really customers or should be customers in this project, not necessarily project managers," Hall said, adding that he was not criticizing their work.

Where the money came from

In November 2023, Princeton voters approved a $109.1 million bond package, including $108.1 million for parks and recreation and $1 million for the Lois Nelson Public Library. The city sold the first $55 million of those parks bonds in summer 2025, alongside $25 million in certificates of obligation for a public safety facility and a fire training tower. The city's 2024-25 budget planned to issue the remaining parks bonds, about $54 million, in the 2026-27 fiscal year.

Don’t miss what’s changing in Princeton.

Get updates on new businesses, city decisions, development projects, and local spending. One clear email every Wednesday.

Free newsletter. Unsubscribe anytime.

Princeton Council Takes On A Staff Gym, A Library Site And A Stack Of Plats ↗

Hall told council the city has roughly $44 million in actual bond proceeds on hand from the 2025 sale, not counting interest, and another $50 million or more scheduled to be issued. The city's most recent quarterly financial report shows $97.9 million sitting in restricted capital project funds as of June 30, 2026. As of Sept. 30, 2025, Princeton carried $134 million in tax-supported debt, according to the city's debt disclosure.

A consultant contract that kept growing

To show the city already pays for this kind of help, Hall pointed to EPT Commercial, an outside project management firm. City records show council approved a professional services agreement with EPT in May 2024 for up to $161,500, tied to the police training facility. Hall said that contract covered "one project" and its scope has been expanded since. Council took up a second amendment in December 2025 and a third in June 2026, and the city's Parks and Recreation Advisory Board reviewed that third amendment in August. Also in June, a separate contract of up to $384,367.60 for EPT to manage construction of the new public safety building went before council.

Hall stressed he was not judging EPT's performance, but said consultants and project managers do different jobs. "These entities are not necessarily charged with the delivery of the project. They're advisors," he said. He said a staff manager would not eliminate outside help entirely, "but it certainly should stop the expansion of the use of these outside entities."

He described a pattern council members have heard before. "I've heard numerous times the frustration of something getting derailed and then it just kind of languishes," Hall said, asking "whose job is it to make sure that that thing stays on track."

The projects in line

Hall listed what is coming: the library, phases two and three of J.M. Caldwell Sr. Community Park, and the city's planned multigenerational building, among other bond projects. Earlier the same night, council voted 6-0 to dedicate six acres in Whitewing Trails for a future library, and voted down gym equipment for the nearly finished Parks and Recreation building after a resident complained that bond-funded parks for the public are lagging. That resident told council the skate park at J.J. Book Wilson Park is not yet open and the recreation center has not broken ground.

Hall called the position budget neutral because bond proceeds would pay for it. He estimated the total cost to the city at about $180,000, which is less than half of 1 percent of the roughly $44 million on hand. Asked by Council Member Terrance Johnson how that works, Hall said it would be a quick reimbursement: "The city would send the bond an invoice for the money the bond would pay for it."

Council Member Cristina Todd said keeping the work in house could save money over time compared with hiring an outside firm for each project. Council Member Jaisen Rutledge asked what happens to the job if the bond projects run out. Hall said that would be a while off and that the person would likely be a construction manager, architect or engineer, with skills that would carry over to other city work.

Council Member Bryan Washington said the city should plan ahead because more borrowing is likely. "At some point we will have to go out for bonds again," he said. Hall agreed. "I know it may be a dirty word to people, but you're going to continue to bond things," he said, noting the city's financial advisors expect a city of Princeton's size to keep issuing debt for roads and other needs. He said this may be the first of more such positions. "But we got to start somewhere," he said.

Hall, who told council he has been the city's interim manager for two months, did not give a hiring timeline for the new position. The city is still searching for a permanent city manager, and Mayor Eugene Escobar Jr. said council expects to meet on that search this Saturday and the next.