Texas Data Centers · September 21, 2026
Texas Hits The Brakes On Data Center Permits
Texas just put another roadblock in front of data center development. Governor Greg Abbott directed the Texas Commission on Environmental Quality to halt permits sought by data centers until the state completes its broader audit of the industry.
For Lavon, that adds a new state-level layer to a data center issue that has already become a major local topic.
No Audit, No State Permit
The September 21 directive tells TCEQ not to move forward with permits sought by data center projects while ERCOT, the Public Utility Commission of Texas and the Texas Water Development Board gather more information.
The state wants a clearer picture of how proposed data centers could affect the electric grid and Texas water supplies before additional regulatory approvals move forward.
Texas Is Looking At More Than Electricity
The audit reaches well beyond how much power a data center could use. State agencies are also examining water consumption, where that water would come from and what water-saving technology projects plan to use.
Abbott had already directed the state on September 14 to step up enforcement of water-use reporting requirements for major users, including data centers. The latest order now ties those reviews directly into the permitting process.
The Rules Are Getting Tougher
The Governor’s directive says data center projects must cover their electrical infrastructure costs, complete the ERCOT audit, report electricity and water usage and comply with setback requirements.
The directive also says data centers must not use water needed by local communities. TCEQ has been told to use information from the ongoing audits when making future permitting decisions.
What This Means For Lavon
This does not decide whether a specific data center can or cannot ultimately be built in Lavon, and it does not replace the city’s own development rules.
|