17 Years Of Negotiations. McKinney Finally Moves Forward On Tucker Hill’s Second Way Out.
McKinney approved Stonebridge Drive extension design from US 380 to Bloomdale. The project includes two bridges and a separate Tucker Hill connection still needed.
Tucker Hill residents could eventually have another route besides US 380 after McKinney City Council approved a $3.44 million engineering contract Nov. 17 for the Stonebridge Drive extension. The project would run north from US 380 to Bloomdale Road alongside the neighborhood, creating the roadway needed for another connection before construction of the US 380 bypass. But residents are still years from using it, and the subdivision must build its own link to the city’s road.
Council Member Patrick Cloutier described the approval as a breakthrough in negotiations involving multiple parties and landowners. “This thing took about 17 years or so to get across the finish line,” he said. Mayor Pro Tem Rick Franklin moved to approve the contract, Cloutier seconded it, and the motion passed. The action authorizes engineering work, with construction still ahead.
A second route, with a gap still to close
Engineering Director Gary Graham told council that Tucker Hill currently gets all its access from US 380. Extending Stonebridge along the subdivision’s western side would provide a north-south route to Bloomdale, giving the neighborhood another option once its internal streets connect to the extension. Graham said the city wants its project finished before TxDOT moves forward with the US 380 bypass.
The city’s road will not complete that connection by itself. “There is still a gap that the subdivision needs to develop to connect their existing subdivision out to the new road,” Graham said. He added that the development was already working on plans for its remaining phases. The city would put the adjacent road in place, while the subdivision would remain responsible for linking its existing streets to it. No opening date for that completed neighborhood connection was established during the discussion.
Two bridges and a roughly $24 million construction estimate
The approved resolution authorizes a $3,438,500 contract with Kimley-Horn and Associates, Inc., with supplemental agreements allowed up to an aggregate contract amount of $3.8 million. That covers engineering services, rather than the entire road project. The staff report carries a separate preliminary construction estimate of $23,963,000 and anticipates additional street funding through general obligation debt in fiscal years 2027 and 2028.
The initial roadway design calls for two lanes between US 380 and Bloomdale, with a full intersection buildout at US 380. Graham described four lanes at that intersection narrowing to two heading north, while the city’s long-range thoroughfare plan identifies the corridor as an eventual four-lane arterial. Sidewalks would extend along the project, with drainage infrastructure, traffic-signal improvements and roadway lighting also included.
Crossing Wilson Creek adds another substantial piece to the work. The engineering scope includes two multi-span bridges, bridge lighting and architectural features, along with analysis of the watershed and water flows needed to design the crossings. Utility coordination, environmental investigations, surveying and right-of-way documents are also included in the contract.
The agreement goes back years. Construction will take more.
The project’s history reaches back to a facilities agreement dated March 17, 2008. A later city term-sheet record describes arrangements involving approximately 1,223.5 acres north of US 380 and south of Bloomdale, addressing public infrastructure and how improvements would be funded. At the Nov. 17 meeting, officials credited staff and multiple landowners with getting the arrangements far enough along for detailed design to proceed. Council had previously approved an alignment-study contract in March 2026.
Detailed design is expected to take about 15 months, with construction potentially beginning in spring 2028. Graham identified March 2030 as the city’s completion obligation under its agreement. For Tucker Hill residents, the engineering approval advances a long-awaited alternative, but construction funding, the road itself and the subdivision’s connecting segment still need to come together before that second route is available.