Collin County voted 4-0 to study new Outer Loop Segment 5 routes to U.S. 380 in Farmersville after the Army Corps signaled it would deny a wetlands permit.

Interactive mode

See this story, step by step.

The same reporting, built as you scroll. Go at your own pace.

Farmersville Weekly

Collin County is going back to the drawing board on the part of the Outer Loop highway planned between Anna and Farmersville.

On Nov. 9, county commissioners voted 4-0 to pay engineering firm HDR to look for new routes for Outer Loop Segment 5. Segment 5 is a planned 21-mile stretch from State Highway 121, between Anna and Melissa, to U.S. 380 in Farmersville.

Don’t miss what’s changing in Farmersville.

Get updates on new businesses, city decisions, development projects, and local spending. One clear email every Wednesday.

Free newsletter. Unsubscribe anytime.

Outer Loop Route Farmersville Fought Gets Axed As A $500K Playground Gets Pitched ↗

The reason is a federal warning. Every route on the table cuts through protected wetland land, and the agency that would have to sign off said no.

"The US Army Corps of Engineers indicated it would deny our permit," Tracy Homfeld of the county engineering department told commissioners.

Which route is which

The county has been comparing colored routes on its maps, which are shown on page 22 of the county's June 2026 public meeting presentation.

Blue is the county's original route. It makes a wide loop to the north and east before heading south. Pink is a slightly adjusted version of blue. Orange cut through the middle of the study area, closer to State Highway 78, and the county has dropped it. Green is a reworked version of orange that also runs through the middle. All of the routes come together north of U.S. 380 and end at 380 near Farmersville.

The problem: protected wetlands

The routes run into the Arnold Creek mitigation banks. A mitigation bank is land that is protected on purpose to make up for wetlands damaged somewhere else. Building a highway through one requires a special federal permit.

HDR found that all three remaining routes would cut into that land. Blue would affect 22.5 acres, pink 22.4 acres and green 61.9 acres.

Homfeld said the Corps told the county it had never approved a permit that affected a mitigation bank. Trying anyway could hold up the project "by three or more years with no guarantee of permit approval," Homfeld said. Making up for the damage could cost "anywhere from nine to $30 million," depending on the route.

Commissioners chose to steer around the wetlands instead.

Farmersville already pushed back

Farmersville sent the county a resolution opposing the orange and green routes because they run too close to State Highway 78, Homfeld said. Blue Ridge opposed the green route over impacts to a school and its wastewater plant. The county dropped orange after its second public meeting, held in Melissa and Blue Ridge.

New routes may hit more homes

HDR has already found several routes that miss the wetlands completely. But Homfeld said they come with a cost: "they do impact more structures." Those details have not been studied yet.

One member of the court said the change will reach people who thought they were safe. "Every one of these lines impacts dozens and even scores of Collin County families," the member said. "Even additional families that might not be on any of these lines might be on the next line."

Another commissioner said there was no point in fighting for a permit. "I don't know that option one's really even a true option," the commissioner said. "No way do I want to hold people's lives up for multiple years."

The routes Farmersville opposed face different odds

The vote helps Farmersville in one way. The green route, which the city opposed, takes by far the most wetland land, nearly three times as much as the others. A commissioner said a crossing that large would make a permit denial more likely, and Homfeld agreed. That makes green the hardest route to build.

But the city's fight isn't over. The Corps told the county the orange route, which Farmersville also opposed, only slightly touches the wetlands, and Homfeld said new routes could reuse part of it. New lines could also run between the two wetland areas or swing around them to the west. Nobody will know where they fall in relation to Farmersville and State Highway 78 until the county shows them.

For people who own property in the area, the uncertainty continues. Homes and land that were never on a map before could end up on the next one.

A January meeting will show the new lines

The county plans a third public meeting in January 2027 to show the new routes. A public hearing to pick a final route would follow in February or March 2027. The county could start buying some land in late summer or fall of 2027. Commissioners asked staff to move faster where they can.

Maps and updates are posted at ccol-segment5.com.