Collin County’s $113 million jail medical and mental health addition is operational. What the construction figure covers, planned beds and future shell space.

Interactive mode

See this story, step by step.

The same reporting, built as you scroll. Go at your own pace.

Collin County’s new jail medical and mental health addition is operational, with staff training nearing completion and the move underway, commissioners were told Nov. 16. The milestone follows state approval to occupy the facility and approximately $113 million in construction costs.

The project adds specialized space for people incarcerated at the county’s Adult Detention Facility in McKinney. County funding records distinguish planned medical and mental health beds from unfinished space reserved for future expansion; those records do not establish how many beds are currently staffed or occupied.

“The total construction cost, including all change orders is approximately $113 million,” Director of Building Projects Sandeep Kathuria told Commissioners Court.

Kathuria said the addition received a temporary certificate of occupancy Sept. 21 and approval from the Texas Commission on Jail Standards to occupy the facility Oct. 1. By the November update, he reported that “staff training is near completion and the move is in progress as we speak.”

Treatment space now, room for future beds

The county’s 2026 recovery plan describes a project providing 125 specialized medical and mental health beds, along with unfinished interior space designed for another 136 beds. That future space should not be counted as an additional 136 beds already staffed and operating.

The same report explains that rising construction costs forced changes to the original plans. One designed wing was removed, and renovation of the existing infirmary was deferred. Unforeseen site conditions also required relocation of utilities and structural components, affecting cost and schedule. The county’s 2026 recovery plan details those changes.

Those changes make older project descriptions an unreliable guide to what opened this fall. Early plans outlined a larger assortment of medical and mental health housing, but the November construction update did not provide a current breakdown of occupied beds, staffing levels or patients receiving care.

A state accessibility filing lists the project at 4300 Community Ave. and identifies approximately 213,142 square feet of work. Its listed construction dates and cost are registration information, rather than confirmation of the opening dates and latest construction total reported to commissioners.

What the $113 million covers

The headline figure is the construction cost, including change orders. It is not presented as the entire cost of designing, equipping, staffing and operating the addition.

The county’s recovery plan lists approximately $136.5 million in funding for the broader medical and mental health project, which also includes related infrastructure such as central plant facilities. That funding scope differs from the construction figure Kathuria reported Nov. 16.

The addition is part of the county’s investment of federal American Rescue Plan Act money in public health facilities. The county’s stated purpose includes expanding medical and behavioral health care capacity for people in custody.

The construction milestone establishes that the new space can be occupied. It does not, by itself, measure improvements in treatment access, waiting times or health outcomes. Those questions depend on how the facility is staffed and used.

Operational, with the transition continuing

Kathuria’s November presentation marked a shift from construction progress to occupancy. State authorization had been received, the facility was operational, and training and the move were still being completed.

He also reported outstanding finishing work across the county’s federally funded building projects as teams worked toward final completion.

For the jail addition, the next measure of progress will be its operation: how much of the specialized space is in use and how the added capacity serves inmates needing medical and mental health care.